| Muhd Azzulfa Jaini | Efficiency | Approval of electrical layout and single line diagram from ABCI/DES | Hello,
I've been waiting since December 2016 for electricity approval for my house.
Description: Lot 64175
Please help follow up. | This complaint has been forwarded to the relevant section | Close | 24/02/2017 08:35 AM | 2 | 01/03/2017 | |
| Azzulfa Jaini | Efficiency | Approval for permanent connection | As'kum and good afternoon, My developer (JFA) has informed me that they are waiting for electrical cable supply from the government for the connection between substation and feeder pillar. It has been 1 month and still no progress.
When can they receive the cable?
My house is on Lot is 64175, Kg Tagap.
Regards, Azzulfa | Waalaikumussalam Tuan, we apologise for the inconvenience. The project owner or developer is responsible for the supply of electrical cable for the connection between substation and feeder pillar. DES has contacted you through email dated 29 July 2017. | Close | 28/07/2017 02:16 PM | 1 | 02/08/2017 | |
| Hjh Maria Binti Abdullah | Efficiency | | Assalamualaikum Bersama ini saya ingin membuat aduan mengenai masalah penyambungan elektrik di Rumah saya No 18 Spg 278 Kg Keramut. Untuk makluman pIhak tuan, pihak contractor telah menghantar borang permohonan pada 13hb Julai 2017 dan sehingga tidak ada menerima maklum balas diberikan mengenai progress tersebut. Untuk makluman pihak tuan , surat untuk pembelian meter prepaid juga belum dikleluarkan. Pihak kami telah beberapa kali datang berjumpa dan menghubungi melalui telefon namun begitu alasan mereka adalah masih on "Q". Adalah sangat diharapkan moga process ini dapat dipercepatkan memandangkan ia melebih dari waktu TROR jabatan DES yang tentukan. | Waalaikumussalam Puan Pihak Jabatan memohon maaf di atas kelambatan proses mendapatkan bekalan elektrik. Walaubagaimanapun, pihak Jabatan telah memberikan kebenaran bagi permohonan Puan pada minggu pertama bulan Ogos 2017. Terima kasih. | Close | 29/07/2017 09:26 AM | 0 | 03/08/2017 | Starting |
| Syai | Efficiency | | power outage at kg mata mata spg 52 is not yet completed from morning, heard that they’re changing the generator and affecting all the surrounding areas even worst during sungkai hours. There is no proper communication either provided to us on how long will this take and just leaving us in the dark. Please do something about this! we’ve been calling 123 numerous times, but no answer cant be given to us. We understood their role is only to coordinate, but please DES , do give information to them so that they can give us the right information and answer on how long will this take and please do your work efficiently.
| | Open | 01/06/2019 07:22 PM | 0 | 06/06/2019 | |
| agen poker bandar ceme | Efficiency | Payment of connection charges | Penjual bandar ceme harus menghadapi kenyataan bahwa agen poker tidak bisa mengendalikan citra online ada sedikit peluang bagi Anda untuk merek produk sebagai milik Anda. Tidak seperti platform agen ceme https://pokerceme.pagexl.com/ agen poker sendiri tidak memiliki etalase untuk merek. Jika Anda tidak memenuhi barang sendiri, pengiriman bahan tidak dapat dicap ke perusahaan unik Sebagai gantinya, branding pasar adalah agen poker https://cemepoker.netlify.com/ online yang utama dan pusat bagi pelanggan. Beberapa pengecer online tidak ingin meluangkan waktu, upaya, dan sumber daya untuk melakukan branding sendiri. Bagi agen poker yang lain, ini adalah kesempatan bandar ceme yang terlewatkan untuk memperkuat citra merek Anda dengan pelanggan online Anda di internet. | | Close | 09/06/2019 01:51 PM | 0 | 14/06/2019 | |